- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 07 April 2022
-
Current Status:
Answered by Jenny Gilruth on 9 May 2022
To ask the Scottish Government how much it has spent on removing the Abellio logo and name from livery, documentation and other parts of the train and rail infrastructure.
Answer
I refer the member to the answer to question S6W-04742 on 13 December 2021. All answers to written Parliamentary Questions are available on the Parliament's website, the search facility for which can be found at /chamber-and-committees/written-questions-and-answers
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 21 April 2022
-
Current Status:
Answered by Jenny Gilruth on 6 May 2022
To ask the Scottish Government, further to the answer to question S6W-02823 by Kate Forbes on 24 September 2021, whether the "rail improvement project" referred to has concluded option selection, in light of it being "on course to conclude option selection by early" in 2022, and what the options are that are being selected from.
Answer
The package of enhancements identified by the project team for taking forward is currently being reviewed by Network Rail’s operations team for Scotland. It comprises signal enhancements, improvements to station approaches and specific capacity alterations to facilitate the mixed operation of faster and slower trains on the same route.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 21 April 2022
-
Current Status:
Answered by Jenny Gilruth on 6 May 2022
To ask the Scottish Government, further to the answer to question S6W-02823 by Kate Forbes on 24 September 2021, what the deliverables are of the rail improvement project that will be completed by the end of 2026.
Answer
The deliverables of the rail improvement project expected to be completed by the end of 2026 will be a capability which will facilitate, subject to changing travel behaviours, timetable and stopping pattern choices, the following options:
? an average journey time of 1 hour 10 minutes or less for inter-city services between Aberdeen and Dundee;
? an average journey time of 2 hours 30 minutes or less for inter-city services between Aberdeen and Glasgow;
? half-hourly services from local stations into Aberdeen and Dundee during peak times;
? an hourly stopping service between Aberdeen and Dundee; and
? new freight paths.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 21 April 2022
-
Current Status:
Answered by Shona Robison on 6 May 2022
To ask the Scottish Government, further to the answer to question S6W-02823 by Kate Forbes on 24 September 2021, whether any eligible housing infrastructure projects have since been submitted as part of the £20 million indicative allocation referred to in the 2016 agreement, and, if not, what has happened to the £20 million indicative allocation.
Answer
A number of City Region Deals include elements of housing infrastructure that is required to unlock wider housing delivery and regional growth ambitions including a notional £20m joint allocation for Aberdeen City and Aberdeenshire Councils. It is the responsibility of Councils to bring forward eligible Housing Infrastructure Fund (HIF) projects to the Scottish Government for consideration. Progress has been slower than anticipated and to date no eligible HIF projects have been submitted by the Councils as part of the £20m indicative allocation referred to in the 2016 agreement. Given the long-term plans for City Deal delivery in the region, and that HIF is open for new applications, Scottish Government officials will remain engaged with both Councils to support them to apply for HIF support where suitable projects through the City Deal delivery plans are identified.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 07 April 2022
-
Current Status:
Answered by Jenny Gilruth on 3 May 2022
To ask the Scottish Government how many outstanding rail passenger compensation claims it is responsible for, as a result of Abellio no longer being responsible for them, broken down by the year in which they were made, and what the total amount of live compensation claims is.
Answer
Up until and including the 31 March 2022 Abellio ScotRail had 2,019 outstanding rail passenger compensation claims, representing a claim value of £9,550. Abellio ScotRail will settle all of these claims.
From 1 April 2022, ScotRail Trains Limited is responsible for considering and settling all new compensation claims.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 04 April 2022
-
Current Status:
Answered by Lorna Slater on 3 May 2022
To ask the Scottish Government, further to the answer to question S6W-07145 by Lorna Slater on 23 March 2022, whether it will now provide the information requested on whether Circularity Scotland has entered into signed contracts with partners to deliver the Deposit Return Scheme's logistics, operations and IT systems, in line with the timescale that it set out in December 2021.
Answer
Circularity Scotland has identified preferred bidders to deliver IT, operations and logistics work and is in intensive discussions with them to finalise the contracts. We expect this to conclude shortly.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 08 April 2022
-
Current Status:
Answered by Michael Matheson on 29 April 2022
To ask the Scottish Government, further to the answer to question S6W-07409 by Michael Matheson on 31 March 2022, whether it will provide the information requested, regarding when it expects projects from the ScotWind offshore wind leasing round to start generating electricity, and what generating capacity, in GW, it anticipates in (a) the first year of operation and (b) each of the following years; for what reason it did not provide this information in its previous response, and what its position is on whether sufficiently detailed planning has been carried out regarding when Scotwind projects are expected to start generating electricity, and what the anticipated generating capacity will be in the first, and each of the following, years.
Answer
Over the next few years each project will go through project development and consenting processes, respond to geographical and technological requirements, and find a route to market. There are several variables to be considered across these processes, including aspects such as grid connection and the impact of offshore wind developments on various environmental receptors.
To add to my response of 31 March 2022, it is not possible at this stage to predict how long each of the 17 ScotWind projects awarded lease options will take to pass through the project development and consenting process, achieve connections to the onshore grid network and subsequently to undergo construction. For each project this is a complex and multi-faceted process involving a number of variables, including the iterative review of offshore wind planning assumptions, impacts arising from environmental assessments, consultative processes, investment decisions with regard to supporting supply chain activity, success in securing power supply agreements though the Contracts for Difference regime, and potential challenges to be addressed in design and construction with regard to physical conditions and the application of innovative floating wind technologies being pioneered at GW scale in a number of projects. These variables are dynamic and are capable of affecting the size and nature of projects as well as the speed at which they will progress. Their impact cannot be predicted with accuracy at this stage.
Forward planning with regard to potential generating capacity, which may be expected from ScotWind and other offshore renewables developments, informs our thinking and is continually reviewed. This type of forward planning will next be reflected in the Government’s Draft Energy Strategy and Just Transition Plan due to be published for consultation this autumn.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 21 April 2022
-
Current Status:
Answered by Kate Forbes on 28 April 2022
To ask the Scottish Government, further to the answer to question S6W-02823 by Kate Forbes on 24 September 2021, how much of the "up to £10 million" that was committed to help extend digital infrastructure across the City Deal region and the City Network Extension project has been spent; what precisely has been achieved with this funding; what precisely it projects will be delivered from the remaining funding, and, in light of the Aberdeen project being "expected to complete later" in 2021, whether it did so, and whether the Full Fibre Project in Aberdeenshire that is expected to complete in 2022 will do so.
Answer
The Memorandum of Understanding for additional investment in the Aberdeen City Region allows for up to £10 million of funding to help extend digital infrastructure across the region. To date £5 million of this funding has been spent.
£2 million was invested in the City Network Extension project which connected 57 council sites to full fibre with build completing in 2021. This investment successfully stimulated around £40 million of commercial investment across the region by CityFibre and Vodafone who are utilising this infrastructure to help extend the reach of full fibre broadband across the region. In January 2022 CityFibre announced a further £19 million of investment in Aberdeen.
£3 million was invested in the Full Fibre Infrastructure project which will connect 192 public sector and NHS sites across Aberdeenshire. To date, 190 sites have been connected with one site expected to be completed in the coming months, and the final site – an additional site made possible by cost savings – to be connected once construction is completed in summer 2023.
We continue to work closely with the Aberdeen City Region Deal team as they develop options for the remaining funding.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 28 March 2022
-
Current Status:
Answered by Michael Matheson on 28 April 2022
To ask the Scottish Government what consideration it has given to the Complementary Climate Delegated Act, regarding taxonomy, approved by the European Commission on 2 February 2022, and whether this will have any impact on its energy policies.
Answer
The Scottish Government is supportive of the ambition within the Green Taxonomy and is carefully considering the legislation to ensure it is in line with SG policy, EU alignment and to ensure that any SI's would not negatively impact Scottish economic activity now or in the foreseeable future.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 04 April 2022
-
Current Status:
Answered by Richard Lochhead on 28 April 2022
To ask the Scottish Government whether the reported delay to the publication of the Just Transition Plan will result in a delay to any aspect of the Just Transition Fund, including in particular the release or application process in connection with the first tranche of £20 million funding, in light of any crossover between individuals who are involved in both the Plan and the Fund.
Answer
There will be no delay to year one of the Just Transition Fund as a result of the revised timetable for publication of the Energy Strategy and Just Transition Plan.