- Asked by: Liam McArthur, MSP for Orkney Islands, Scottish Liberal Democrats
-
Date lodged: Wednesday, 26 February 2025
-
Current Status:
Answered by Angela Constance on 5 March 2025
To ask the Scottish Government whether it sought or received any expert advice on construction cost controls for the replacement of HMP Inverness and, if so, whether it will publish this.
Answer
I have asked Teresa Medhurst, Chief Executive of the Scottish Prison Service (SPS), to respond. Her response is as follows:
The SPS engaged the services of legal advisers and cost consultants to advise on cost controls within the contract. It would not be appropriate for SPS to publish this advice as it is commercially sensitive information, however, SPS will publish a summary of their Business Case on their website.
- Asked by: Liam McArthur, MSP for Orkney Islands, Scottish Liberal Democrats
-
Date lodged: Thursday, 06 February 2025
-
Current Status:
Answered by Angela Constance on 4 March 2025
To ask the Scottish Government, in light of the potential number of people who could be eligible for the new national throughcare service for prisoners released from (a) short-term sentences or (b) remand, what criteria or prioritisation methods will be used to determine who receives immediate support.
Answer
The new national service will ensure that an offer of support is available to all eligible individuals who are serving a short sentence (under 4 years), or being held on a period of remand.
As with the current Shine and New Routes Public Social Partnership services, the new service will be voluntary, and individuals will have a choice about whether they wish to sign up to the service.
Dedicated prison-based workers will provide initial support during the custodial environment and will contribute to effective multi-agency pre-release planning. Prior to liberation, individuals will be introduced to their community worker who will provide support on release.
- Asked by: Liam McArthur, MSP for Orkney Islands, Scottish Liberal Democrats
-
Date lodged: Friday, 21 February 2025
-
Current Status:
Answered by Angela Constance on 4 March 2025
To ask the Scottish Government whether it will publish a full breakdown of the costs associated with the replacement for HMP Barlinnie, including any penalties for delays.
Answer
SPS are unable to publish the full breakdown of costs as disclosure would be commercially prejudicial to the management of the contract, and to the contractor.
SPS can confirm that the contract contains liquidated damages for any delays.
- Asked by: Liam McArthur, MSP for Orkney Islands, Scottish Liberal Democrats
-
Date lodged: Wednesday, 26 February 2025
-
Current Status:
Answered by Angela Constance on 4 March 2025
To ask the Scottish Government whether it will publish a full breakdown of costs associated with the replacement for HMP Inverness, including any penalties for delays.
Answer
The SPS engaged the services of legal advisers, cost consultants, insurance brokers and geo-technical consultants to advise on cost controls within the contract. It would not be appropriate for SPS to publish this advice as it is commercially sensitive information, however SPS will publish a summary of their Business Case on their website.
- Asked by: Liam McArthur, MSP for Orkney Islands, Scottish Liberal Democrats
-
Date lodged: Friday, 21 February 2025
-
Current Status:
Answered by Angela Constance on 4 March 2025
To ask the Scottish Government how many prisoners will be released early from HMP Barlinie due to overcrowding while the replacement prison for it remains incomplete.
Answer
I have asked Teresa Medhurst, Chief Executive of the Scottish Prison Service (SPS), to respond. Her response is as follows:
SPS will publish information on the early release under the changes to sentencing for short-term prisoners on our website, and we have previously published information on releases under the emergency release legislation again on their website.
SPS seek to be as open and transparent as possible, whilst continuing to meet our statutory obligation to ensure that those in our care have their personal information protected; as such we cannot publish a breakdown of establishments as some of the data could relate to a small group of individuals, which may lead to their inadvertent identification.
- Asked by: Liam McArthur, MSP for Orkney Islands, Scottish Liberal Democrats
-
Date lodged: Friday, 21 February 2025
-
Current Status:
Answered by Angela Constance on 4 March 2025
To ask the Scottish Government what assessment it has made of the impact of the delay to the replacement of HMP Barlinnie on (a) prison overcrowding and (b) early release policies.
Answer
SPS will publish information on the releases under the changes to sentencing for short-term prisoners on their website and SPS has previously published information on releases under the emergency release legislation also on their website.
SPS continue to be as open and transparent as possible, whilst continuing to meet their statutory obligation to ensure that those in their care have their personal information protected; as such SPS cannot publish a breakdown of establishments as some of the data could relate to a small group of individuals, which may lead to their inadvertent identification.
- Asked by: Liam McArthur, MSP for Orkney Islands, Scottish Liberal Democrats
-
Date lodged: Friday, 21 February 2025
-
Current Status:
Answered by Angela Constance on 4 March 2025
To ask the Scottish Government on what dates since 2014 it has received an updated timescale for the completion of HMP Glasgow, and what the revised date given was at each update.
Answer
The Scottish Government has received regular updates from the Scottish Prison Service on HMP Glasgow in line with updates to the Infrastructure Investment Plan since 2014:
- In March 2014 the Scottish Government was updated that there was an on-going site search and completion dates for the project remained uncertain.
- In March 2016 the Scottish Government was updated that estimated operational date was 2022.
- In September 2016 the Scottish Government was updated that estimated operational date was 2023.
- In April 2019 the Scottish Government was updated that estimated operational date was 2024.
- In November 2020 the Scottish Government was updated that estimated operational date was 2026.
- In May 2023 the Scottish Government was updated that the project time-line was uncertain.
- In July 2023 the Scottish Government was updated that the most likely time-scale for construction completion was 2027 but there were risks associated with this.
- In May 2024 the Scottish Government was updated that the most likely time-scale for construction completion was 2028.
- Asked by: Liam McArthur, MSP for Orkney Islands, Scottish Liberal Democrats
-
Date lodged: Friday, 21 February 2025
-
Current Status:
Answered by Angela Constance on 4 March 2025
To ask the Scottish Government how many assaults on (a) staff and (b) prisoners have been recorded at HMP Barlinnie in each of the last five years.
Answer
I have asked Teresa Medhurst, Chief Executive of the Scottish Prison Service (SPS), to respond. Her response is as follows:
The number of assaults on staff in HMP Barlinnie in the last 5 years are as follows:
HMP Barlinnie |
Year | Staff |
2020 | 35 |
2021 | 49 |
2022 | 30 |
2023 | 45 |
2024 | 63 |
The number of assaults on Prisoners in Barlinnie in the last 5 years are as follows:
HMP Barlinnie |
Year | Prisoner |
2020 | 123 |
2021 | 163 |
2022 | 117 |
2023 | 120 |
2024 | 253 |
- Asked by: Liam McArthur, MSP for Orkney Islands, Scottish Liberal Democrats
-
Date lodged: Friday, 21 February 2025
-
Current Status:
Answered by Angela Constance on 4 March 2025
To ask the Scottish Government what discussions it has had with the Scottish Prison Service regarding contingency plans for managing HMP Barlinnie while its replacement is delayed.
Answer
The Scottish Government has regular discussions with the Scottish Prison Service (SPS) on risks and contingency plans for the prison estate, including HMP Barlinnie.
In response to recommendations made by HM Chief Inspector of Prisons for Scotland, SPS took forward HMP Barlinnie Programme of Works which significantly improved facilitates within the prisoner reception and healthcare areas. These works concluded in April 2023.
- Asked by: Liam McArthur, MSP for Orkney Islands, Scottish Liberal Democrats
-
Date lodged: Friday, 21 February 2025
-
Current Status:
Answered by Angela Constance on 4 March 2025
To ask the Scottish Government which contractors bid to build HMP Glasgow.
Answer
This was a 2-stage procurement process, and 4 contractors bid at the 1st stage Pre-construction phase of the process. These bidders were Balfour Beatty Group, Graham Construction, Kier Construction and Laing O'Rourke.