- Asked by: Liam McArthur, MSP for Orkney, Scottish Liberal Democrats
-
Date lodged: Monday, 07 September 2009
-
Current Status:
Answered by Jim Mather on 18 September 2009
To ask the Scottish Executive whether it considers it good practice to consider a planning application for a coal-fired power station before it has produced its thermal generation guidance.
Answer
Under section 36 of the Electricity Act 1989, Scottish ministers are obliged to accept and consider all thermal power station applications in excess of 50 megawatts of generating capacity. Each application is subject to statutory consultation with the determination taking into account all material issues, including the thermal guidance applicable at the time the decision is made.
- Asked by: Liam McArthur, MSP for Orkney, Scottish Liberal Democrats
-
Date lodged: Monday, 07 September 2009
-
Current Status:
Answered by Jim Mather on 18 September 2009
To ask the Scottish Executive, given that it has yet to produce its thermal generation guidance, on what basis it will consider the planning application for the Hunterston power plant.
Answer
All thermal power station applications over 50 megawatts in generating capacity will be considered by Scottish ministers under section 36 of the Electricity Act 1989. Following a request from Ayrshire Power Limited, Scottish Ministers provided a scoping opinion on 20 March 2009 on the Hunterston project, which included a wide range of consultee advice on the outline design. The developer is currently working in partnership with stakeholders to develop an application which addresses the relevant planning, community and legislative issues, and we have recommended to the developer that they take into account in any application our draft guidance and the answer to question S3W-
24912 on 17 June 2009.
All answers to written parliamentary questions are available on the Parliament''s website, the search facility for which can be found at .
- Asked by: Liam McArthur, MSP for Orkney, Scottish Liberal Democrats
-
Date lodged: Monday, 07 September 2009
-
Current Status:
Answered by Jim Mather on 18 September 2009
To ask the Scottish Executive whether it considers it premature to consider a planning application for a development, for the basis of which it has not formulated policy.
Answer
Under section 36 of the Electricity Act 1989, the building of any new thermal power station in excess of 50 megawatts in generating capacity would require consent from Scottish ministers. The Scottish Government published draft thermal guidance in late 2008 for consultation. We await the completion of the UK Government consultation, before publishing our final thermal guidance in Scotland.
- Asked by: Liam McArthur, MSP for Orkney, Scottish Liberal Democrats
-
Date lodged: Monday, 07 September 2009
-
Current Status:
Answered by Jim Mather on 18 September 2009
To ask the Scottish Executive when it expects to produce its thermal generation guidance.
Answer
The Scottish Government will issue its final thermal guidance later this year following consideration of responses to our own consultation and the subsequent UK consultation which closed on 9 September 2009.
- Asked by: Liam McArthur, MSP for Orkney, Scottish Liberal Democrats
-
Date lodged: Monday, 07 September 2009
-
Current Status:
Answered by Jim Mather on 18 September 2009
To ask the Scottish Executive what progress has been made on the development of an emissions performance standard for power plants in Scotland.
Answer
The question of an emissions performance standard was raised in response to our consultation on draft thermal guidance last year. It was also discussed in the recent UK consultation on clean coal. Responses to this consultation have been copied to the Scottish Government. We are working closely with the UK Government on this matter and will consider our position once this process is complete.
- Asked by: Liam McArthur, MSP for Orkney, Scottish Liberal Democrats
-
Date lodged: Monday, 07 September 2009
-
Current Status:
Answered by Jim Mather on 18 September 2009
To ask the Scottish Executive how its plans for the development of carbon capture and storage and emissions performance standards for power stations take into account the emission reduction targets in the Climate Change (Scotland) Act 2009.
Answer
The climate change delivery plan sets out four transformational outcomes which the Scottish Government is working towards. The first of these is a largely de-carbonised electricity generation sector by 2030, primarily using renewable sources for electricity generation with other electricity generation from fossil fuelled plants utilising carbon capture and storage. The development of carbon capture and storage (CCS) is one of our ten energy pledges and CCS and other low carbon technologies will play a vital role in meeting that challenge.
- Asked by: Liam McArthur, MSP for Orkney, Scottish Liberal Democrats
-
Date lodged: Monday, 07 September 2009
-
Current Status:
Answered by Jim Mather on 18 September 2009
To ask the Scottish Executive for what reason proposals for a coal-fired power station at Hunterston were not included in the public consultation on the second National Planning Framework.
Answer
I refer the member to the answer to question S3W-27009 on 18 September 2009. All answers to written parliamentary questions are available on the Parliament''s website, the search facility for which can be found at .
- Asked by: Liam McArthur, MSP for Orkney, Scottish Liberal Democrats
-
Date lodged: Friday, 04 September 2009
-
Current Status:
Answered by Richard Lochhead on 18 September 2009
To ask the Scottish Executive whether it supports the withdrawal of EU funding from compensation for withdrawals and buy-ins, as proposed in amendment 5258 to the EU agriculture budget.
Answer
Withdrawals and buy-ins has received only limited use in Scotland. Should the proposed amendment be adopted, the Scottish Government anticipate that it would not have a significant impact in Scotland.
- Asked by: Liam McArthur, MSP for Orkney, Scottish Liberal Democrats
-
Date lodged: Monday, 07 September 2009
-
Current Status:
Answered by Jim Mather on 18 September 2009
To ask the Scottish Executive when it was decided to include Hunterston power station in the second National Planning Framework and what consultation has been carried out on its inclusion.
Answer
A new clean coal power station and a transhipment hub at Hunterston were among the projects proposed by stakeholders as additional national developments in representations on the NPF Discussion Draft. These projects were assessed against the criteria for national developments announced in a statement to Parliament by the Cabinet Secretary for Finance and Sustainable Growth in September 2007 and subsequently included amongst the candidate national developments which were subject to a Supplementary Strategic Environmental Assessment, including consultation, in autumn 2008. The NPF has also been the subject of detailed consideration by three committees of the Scottish Parliament and a debate in Parliament on 5 March 2009, ensuring a high level of scrutiny of the spatial strategy and national developments. The National Planning Framework Participation Statement available on the Scottish Government''s website details the full extent of consultation during the preparation of NPF2.
- Asked by: Liam McArthur, MSP for Orkney, Scottish Liberal Democrats
-
Date lodged: Friday, 04 September 2009
-
Current Status:
Answered by Richard Lochhead on 18 September 2009
To ask the Scottish Executive whether the Scotland Rural Development Programme includes measures for conservation and sustainable use of biodiversity in agriculture.
Answer
There are a range of measures to support conservation and sustainable use of biodiversity in agriculture in a number of Scotland Rural Development Programme schemes, including Rural Priorities and Land Managers'' Options. More information is available on the SRDP website at .